PUD-8-15 Joe Kemp Construction, LLC 2400 S. Adams St
Site plan approval for single family and multi-family dwelling units on 27.98 acres of Sudbury Parcel O. Also requested is preliminary plat approval.
Case Manager: Eric Greulich
ITEM FOR THE CONSENT AGENDA:
ZO-6-15 City of Bloomington
Hear a request for amendments to the Unified Development Ordinance (UDO) to transfer authority regulating temporary food and beverage sales to Title 4 of the Bloomington Municipal Code as well as minor amendments to the regulation of Temporary Uses.
Case Manager: Tom Micuda
SP-7-15 ERL-2, LLC
632 N College Ave
Site plan review for an addition to a 3-unit multi-family building.
Case Manager: Jim Roach
PETITIONS:
SP-2-15 Monroe County Commissioners 312 N. Morton St.
Site plan to allow construction of an 8-story parking garage.
Case Manager: Patrick Shay
PUD-1-15 Eastside Investments, LLC. 901 N. Smith Rd.
Preliminary plan and district ordinance amendment of a planned unit development (PUD) to revise the list of approved uses.
Case Manager: Patrick Shay
PUD-5-15 Simon Property Group 2894 E 3rd St
Final plan amendment to allow partial reconstruction, two new outlets and revised sign package at the College Mall Planned Unit Development (PUD).